How to calculate the expected monetary value of your project

From Team '23

Tempo Team

Harnessing the power of expected monetary value (EMV) analysis is crucial for navigating the unpredictable seas of risk and uncertainty.

This analytical approach is a key component in a project manager’s tool kit, alongside other crucial tools like risk registers and Strengths, Weaknesses, Opportunities, and Threats (SWOT) assessments. By quantifying the possible cost or payoff of identified risks, EMV analysis provides a clear financial perspective on how these risks impact the project and the organization. Its integration into risk management processes also helps project leaders identify and respond to threats, informing the project’s contingency plan and overall success.

What’s expected monetary value?

EMV is a risk analysis tool that evaluates the financial impact of potential events on a project’s outcome and the company’s financial health. It operates by multiplying an event’s probability with its impact, clearly estimating potential losses and gains for each scenario. This holistic approach — meaning EMV accounts for various factors — enables project managers to evaluate and compare different strategies for mitigating risk. This helps them make informed, data-driven decisions to prioritize the most effective risk response strategies.

Why use expected monetary value in project management?

EMV in project management enhances decision-making and risk assessment. This analysis type also offers the following benefits:

  • Simplicity: The EMV formula is uncomplicated. You can use simple pencil-and-paper calculations to assess and address risks promptly.

  • Prioritization: Project managers can identify and concentrate on the most critical threats that could significantly alter project outcomes by assigning a monetary value to potential risks.

  • Resource allocation: EMV helps distribute resources effectively. It identifies crucial risks so you can strategically allocate resources toward areas of greatest need first.

  • Cost-benefit analysis: The EMV calculation also evaluates the cost-efficiency of various response strategies. This analysis helps you select the most effective approaches, enhancing overall risk management efficiency.

Limitations of the expected monetary value analysis

While EMV is a valuable tool in project management, it has certain constraints:

  • Assumptions: EMV often assumes that all potential scenarios have an equal likelihood of occurring. Inaccuracies can arise if specific occurrences aren’t accurately accounted for in the calculations.

  • Focus on financial factors: Since EMV primarily considers financial outcomes, its singular focus can sometimes lead to less ethical or socially responsible decisions, especially in crisis situations.

  • Data accuracy: The reliability of EMV calculations depends heavily on the accuracy of the historical data used. Limited or flawed data on outcome probabilities can compromise the analysis.

  • Potential for bias: The analysis can become distorted if decision-makers can’t maintain objectivity or the data skews to favor a particular outcome.

How to calculate EMV: 4 steps

Calculating EMV is a straightforward, four-step process. Work with your team throughout to ensure you’re considering various perspectives and including a comprehensive dataset.

1. Identification

Collaborate with your project team to pinpoint every potential risk and its outcomes. This includes assessing each risk’s positive and negative impacts. After compiling a comprehensive list, estimate the likelihood of each scenario, presenting these probabilities as percentage values.

2. Valuation

Review your list and assign a monetary impact value to each identified risk. In scenarios where direct financial assessment isn’t applicable, such as customer experience decisions, use a point system or satisfaction score as a substitute.

3. Calculation

After defining all variables, calculate the EMV for each risk by multiplying its impact by its probability (expressed as a percentage). The formula looks like this:

EMV = Probability × Impact

4. Summation

Add up the EMV values of all identified risks to arrive at an overall total for the project. This sum reflects the project’s cumulative risk in monetary terms.

Expected monetary value examples

Decision-making in project management is fraught with uncertainty, making risk assessment techniques like the EMV analysis essential to limiting and mitigating their impact. Here are practical examples where this approach provides valuable insights.

Quantifying threats and opportunities

Two weeks into a six-month-long project, you learn that your programming lead may need to take an unexpected leave. You assess the risk of them needing early leave and calculate the cost of hiring a temporary replacement:

Probability of risk = 10.5% Financial impact of risk = -$1,400 per week for 8 weeks EMV calculation = Probability × Impact EMV = – ($1,400 × 8 weeks) × 10.5% EMV = -$11,200 × 10.5% EMV = -$1,176

So, if you were to replicate this project scenario 100 times, you can anticipate an average additional expense of $1,176 each time arising from this risk.

Another example is working on a project with an 8% chance that your supplier will reduce material costs by 5%, potentially saving $15,000:

Probability of risk = 8% Financial impact of risk = +$15,000 EMV = Probability × Impact EMV = +$15,000 × 8% EMV = +$1,200

Here, the average savings for 100 projects with this supplier would be $1,200 stemming from reduced resource costs.

Establishing a contingency fund

Projects often include a contingency fund for unforeseen risks. Not every threat will materialize, so this fund’s value equals the sum of all EMV calculations.

EMV #1 – Supplier files for bankruptcy = -$2,000 EMV #2 – Staff turnover = -$1,000 EMV #3 – Supply chain delays = -$850

ΣEMV = EMV#1 + EMV#2 + EMV#3 ΣEMV = (-$2,000) + (-$1,000) + (-$850) ΣEMV = -$3,850

So, a contingency fund of $3,850 would be set aside to cover these financial risks.

Create a decision tree

A decision tree is a tool for multivariable analysis in project management, laying out different paths and their potential outcomes. When faced with a choice, such as refurbishing existing equipment or investing in new technology, a decision tree helps visualize the financial implications of each route.

Let’s explore three options — refurbishing existing equipment or choosing between two new technology alternatives. For each option, we’ll examine the initial investment required and the potential return. These figures are crucial for calculating the EMV for each scenario — optimistic, likely, and pessimistic — branching from each option. When branches meet, they form a node, indicating a decision point.

  • Option 1 (Refurbishing equipment): We’ll look at the refurbishment costs (initial investment) and the potential increased efficiency or revenue (return).

  • Option 2 (New technology, candidate #1): Here, we compare the price of acquiring new tech (initial investment) against the anticipated benefits it brings (return).

  • Option 3 (New technology, candidate #3): Similar to Option 2, but with different costs and potential returns based on this specific technology choice.

We’ll delve into the most optimistic, likely, and pessimistic outcomes for each option, calculating their EMV based on their initial investment and projected return.

Option 1 – Refurbished equipment

  • Optimistic outcome = Tech exceeds expectations

    Net impact = Return – Initial investment

    Net impact = $120,000 – $50,000

    Net impact = +$70,000

    Probability = 10%

    EMV = $70,000 × 10%

    EMV = +$7,000

  • Likely outcome = Tech meets expectations

    Net impact = Return – Initial investment

    Net impact = $100,000 – $50,000

    Net impact = +$50,000

    Probability = 60%

    EMV = +$50,000 × 60%

    EMV = +$30,000

  • Pessimistic outcome = Tech fails, requiring extra time and upgrades

    Net impact = Return – (Initial investment + Cost of new equipment)

    Net impact = $100,000 – ($50,000 + $200,000)

    Net impact = -$150,000

    Probability = 30%

    EMV = -$150,000 × 30%

    EMV = -$45,000

  • ∑EMV = +$7000 + $30,000 – $45,000

    Option 1 ∑EMV = -$8,000

Option 2 – New technology, Candidate #1

  • Optimistic outcome = Tech exceeds expectations

    Net impact = Return – Initial investment

    Net impact = $250,000 – $200,000

    Net impact = +$50,000

    Probability = 15%

    EMV = +$50,000 × 15% EMV = +$7,500

  • Likely outcome = Tech meets expectations

    Net impact = Return – Initial investment

    Net impact = +$220,000 – $200,000

    Net impact = +$20,000

    Probability = 80%

    EMV = $20,000 × 80%

    EMV = +$16,000

  • Pessimistic outcome = Tech fails, requiring extra time and upgrades

    Net impact = Return – (Initial investment + Cost of upgrades)

    Net impact = $220,000 – ($200,000 + $65,000)

    Net impact = -$45,000

    Probability = 5%

    EMV = -$45,000 × 5%

    EMV = -$2,250

  • ∑EMV = +$7,500 + $16,000 – $2,250

    Option 2 ∑EMV = +$25,250

Option 3 – New technology, Candidate #2

  • Optimistic outcome = Tech exceeds expectations

    Net impact = Return – Initial investment

    Net impact = $240,000 – $200,000

    Net impact = +$40,000

    Probability = 20%

    EMV = $40,000 × 20%

    EMV = +$8,000

  • Likely outcome = Tech meets expectations

    Net impact = Return – Initial investment

    Net impact = $225,000 – $200,000

    Net impact = +$25,000

    Probability = 65%

    EMV = +$25,000 × 65%

    EMV = +$16,250

  • Pessimistic outcome = Tech fails, requiring extra time and upgrades

    Net impact = Return – (Initial investment + Cost of upgrades)

    Net impact = + $225,000 – ($200,000 + $70,000) Net impact = -$45,000

    Probability = 15%

    EMV = -$45,000 × 15% EMV = -$6,750

  • ∑EMV = + $8,000 + ($16,250 + (- $6,750)) Option 3 ∑EMV = +$17,500

When you these outcomes together into a decision tree, it’ll look like:

Expected monetary value template UI

When compiled into a decision tree, these outcomes clearly indicate that Option 2 emerges as the preferable choice. Although Option 3 presents similar EMVs for the likely and pessimistic scenarios, it carries a higher failure risk and yields a lower overall EMV.

Effective risk management with Tempo

Ensure the accuracy of EMV calculations by outlining each step of your project’s execution with an audience-friendly roadmap. Whether you work in strategic planning, product development, or project management, roadmapping with Tempo’s Strategic Roadmaps software helps you track every task within your initiative and identify potential risks and rewards. And you’ll also have the information necessary to prioritize mitigation tasks and integrate feedback into your execution plan.

Tags

  • Strategic Roadmaps

Strategic Roadmaps

Strategic roadmapping

Build your portfolio vision with Strategic Roadmaps. With powerful visualization capabilities, you can communicate strategy to the entire organization and gain alignment around strategic objectives, product goals, and milestones.

Start a Free Trial
Special Offer

Explore More Content

Align your organization with proactive portfolio management

Portfolio Manager (LiquidPlanner)

Predictive scheduling and the ability to forecast project timelines and spot risks so you can meet deadlines with confidence.

Learn more

No-code Tableau Jira integration

Tableau Connector for Jira

Effortlessly bridge Jira with Tableau, unlocking unparalleled insights and enhancing decision-making

Learn more

Jira Portfolio Management PPM

Structure by Tempo

Jira Project Portfolio Management (PPM): Visualize data and manage projects within spreadsheet-like tables — in less than a minute

Go to marketplace

Powered by Structure’s custom hierarchies, visualize your roadmap, project plans, timeline & dependencies within Jira Gantt charts

Go to marketplace

No more reporting limitations

Custom Charts for Confluence

Create and share all kinds of highly visual and customizable charts directly on your Confluence pages.

Learn more

Get the data you need to succeed

Time Tracker

Extend your Jira with prebuilt and highly configurable reports for straightforward time tracking.

Learn more

Time Tracking Software for Jira

Timesheets

Tempo’s intuitive automation and Jira-native design make it the most trusted time tracking tool for enterprise organization.

Learn more

Custom charts and dashboards for Jira

Custom Charts for Jira

See how work is progressing and where blockers are with the most flexible reporting app in Jira.

Learn more

Project and program management for Jira

Structure PPM

Visualize all your Jira data & manage portfolios of projects in real-time.

Learn more

Real-time collaboration and capacity planning in Jira

Capacity Planner

A powerful team resource management tool designed to optimize capacity planning and project management in Jira

Learn more

Industry-leading project plan and roadmap visualizations with a Gantt chart extension

Gantt Charts for Structure PPM

Visualize project plans and roadmaps with a Gantt chart extension for Jira

Learn more

Ensure compliance and optimize spending

Governance and auditing

Portfolio governance and auditing excellence

Learn more

Unified time and team management

Timesheets and Structure

Combining Tempo Timesheets and Structure PPM provides a unified view of time tracking and project progress, enabling more accurate reporting and effective portfolio management. Simplify workflows, enhance collaboration, and ensure projects stay on time and within budget.

Learn more

Jira Team & Resource Management

Capacity Planner

#1 Jira Resource Management App: Optimize team allocation, skillset utilization, capacity planning & project management

Go to marketplace

No-code Power BI ServiceNow integration

Power BI Connector for ServiceNow

Seamlessly connect ServiceNow with Power BI, transforming complex enterprise data into actionable insights and driving smarter, data-informed decisions across the organization

Learn more
Colleagues interacting around a desk

No-Code Power BI Jira Integration

Power BI Connector for Jira

Effortlessly bridge Jira with your preferred BI tool, unlocking unparalleled insights and enhancing decision-making

Learn more

Agile at Scale Software

Agile at Scale

Adapt to changing business needs, rapidly adjust plans, and reallocate investment.

Learn more

Unified time and team management

Timesheets and Capacity Planner

Seamlessly manage project timelines and resources while accurately tracking time spent on tasks. This integration enhances visibility, improves planning accuracy, and supports data-driven decision-making for better overall project outcomes.

Learn more

Jira ITSM Solutions with Tempo

ITSM

Build and scale a custom ITSM solution at your own pace with Tempo's modular suite of integrated tools. Enhance Jira's capabilities and take control of your entire IT portfolio.

Learn more

Roadmapping software for teams of all sizes

Strategic Roadmaps (Roadmunk)

The roadmapping tool designed for high-performing teams delivering boardroom-ready strategic roadmaps.

Learn more

Strategic Portfolio Management

Strategic Portfolio Management

Modern modular PPM solutions that scale with your business. Align your teams with the integrated platform that bridges the gap between strategy and execution.

Learn more

Never lose track of a brilliant idea again

Idea Manager for Strategic Roadmaps

Never lose a brilliant idea again. Idea Manager for Strategic Roadmaps has built-in best practices to help.

Learn more

Monitor financial health at every level

Financial Manager

Monitor projects and portfolios to get simple, clear, and real-time views of your costs, budgets, and profits that can be shared throughout your entire organization.

Learn more

Align strategy and execution

Structure PPM and Strategic Roadmaps

For planning leaders looking to add a big-picture roadmap view to their structured Jira data, this integration is essential. Improve visibility to leadership, reduce reporting admin, and keep your team aligned.

Learn more

Jira Time Tracking

Timesheets by Tempo

#1 Jira Time Tracking & AI Apps: Log Tempo Timesheets for Planning, Project Management & Billing. Plugin Office365, Google & Slack

Go to marketplace

No-code BigQuery Jira integration

BigQuery Connector for Jira

Integrate Jira with Google BigQuery to seamlessly export and sync data for advanced analytics and customized reporting

Learn more

Centralize real-time plans in one view

Structure and Gantt Charts

Gain a more complete project management solution, simplifying project reporting, improving collaboration, and ensuring projects stay on time and within budget.

Learn more
Team working together at board with sticky notes

No-code Power BI monday.com integration

Power BI Connector for monday.com

Get powerful data export capabilities and connect monday.com to Power BI effortlessly

Learn more

Strategic portfolio management for PMO leaders

Strategic portfolio management for PMO leaders

Tempo gives PMO directors and portfolio managers the tools to reduce delivery friction, align teams, and drive measurable outcomes.

Learn more

Take control of your projects

Portfolio Manager and Jira

Portfolio Manager integrates seamlessly with Jira to give you predictive scheduling, real-time scenario modeling, and advanced resource management – ensuring you stay on track, no matter what challenges arise.

Learn more

Jira Project Cost Tracking

Financial Manager

Project financial management for Jira & Timesheets. Monitor project costs, expenses, revenue, billing & budgets. Track Capex/Opex

Go to marketplace