How to conduct a risk assessment for your project

One of the biggest challenges of project management is dealing with risks and opportunities. How do I build a work breakdown structure if I don’t know what’s going to be a problem down the road?

How do I build my team if the challenges are unknown? How do I effectively leverage good news? The difference between success and failure can come down to proper management of your risks and opportunities.

Silhouette of a tightrope walker balancing on a wire stretched between skyscrapers, symbolizing risk-taking, precision, and overcoming challenges in high-stakes environments.

First, it’s important to understand the difference between an issue and a risk. A risk is something that might happen, while an issue is something that has happened. For example, climate change is an issue; an extinction-level asteroid strike in the next 100 years is a risk.

The first step to managing risks is to identify them early and take actions that reduce them, known as mitigations. A key tool to help you manage risk is a Failure Mode Effects Analysis (FMEA). You use this to find and prioritize your risks.

There are four stages to building your FMEA:

1. What are the risks that might arise during the project?

2. How important are these risks?

3. How should we respond to these risks?

4. Mitigate

What are the risks that might arise during the project?

Gather a group of people, some who understand the project well, but also a couple pairs of fresh eyes. All the disciplines that are involved in the project should be represented, possibly including engineering, manufacturing, sales, support, and marketing.

Once you’ve gathered the group, it’s time for some brainstorming. Just ask, “How could something go wrong (or right) that is a deviation from our plan?”

I like to break the problem into categories, like mechanical and electrical, to help make sure every area of the project is touched upon. No risk is too small, and everything is added to the list without filtering. There’s just enough discussion that the team agrees what the risk is and the text is unambiguous.

Let everything sit for a few days. It’s not unusual for someone to email you with more ideas after the meeting. That’s great, it’s a sign that the team is taking the exercise seriously. Just add everything to the list.

As an example, if you’re building an electrically powered device with a pressure vessel, your risks might include:

Area

Risk/Opportunity

Mechanical

Pressure vessel fails

Electrical

Power demand exceed requirements

Thermal

Temperature exceeds material limits

Mechanical

Weight exceeds requirement

Table 1: List of risks from brainstorming session

How important are these risks?

After a few days, convene the group again. Add any ideas for risks that have occurred to people since the last meeting, but don’t restart the brainstorming.

Then it’s time to get to the hard part, quantifying the risks for severity and probability. First, set the ground rules. Each risk should be rated on a 1 to 5 scale for severity and probability. Some teams like a 1 to 3 or 1 to 10 scale, but I find 1 to 5 provides the right amount of precision.

The exact definitions can vary, so it’s important to define them for the project you’re scoring. You should have something like this:

Severity

Impact

1

Minor impact to lifespan of product or functionality. Probably not noticed by end-user.

2

Some impact to lifespan of product or functionality. May be noticed by end-user, but not sufficient to create a poor impression.

3

Impacts the lifespan of product or functionality. Will be noticed by end-user and may lead to poor reviews.

4

Significant impact to the lifespan of product or functionality. Will lead to warranty returns and poor reviews.

5

Creates a safety hazard to the end-user.

Table 2: Severity will be different if the worst case is triggering a Richter 7 Earthquake or having to reboot your computer. Severity 5 is the worst thing that can happen and scale down from there.

Probability

Impact

1

Happens 1/1,000,000 per unit per year

2

Happens 1/100,000 per unit per year

3

Happens 1/10,000 per unit per year

4

Happens 1/1,000 per unit per year

5

Happens 1/100 per unit per year (if you have 100 units in the field, you’d expect to see this once per year

Table 3: The probability should be scaled based on the number of units you expect to deploy. A probability of 1 should be rare, but not never, while a probability of 5 should be often, but not all the time. The above example would be appropriate for a device that sells about 100,000 per year.

Some teams include Discoverability (i.e. the difficulty of determining if the risk has happened). I find that adds more complexity, but not a lot of value. It also lowers the relative RPN of risks that are easy to discover, which might lower the priority of a critical risk.

You now go through each risk and rate how likely you think it is to happen and the severity (positive or negative) if it does.

Everyone needs to understand that these are Scientific Wild-Ass Guesses (not to be confused with a Stupid Wild-Ass Guess): Don’t spend a lot of time arguing whether it should be a 3 or a 4. Just put down a consensus number and keep moving forward.

When in doubt, go with the higher number. You also need to calculate the Risk Priority Number (RPN), which is the Severity x Probability, for each risk. When you’re done you should sort the risks by RPN.

Do not discuss how to solve the problems at this meeting.

Area

Risk/Opportunity

Severity

Prob

RPN

Thermal

Temperature exceeds material limits

5

2

10

Mechanical

Pressure vessel fails

5

2

10

Electrical

Power demand exceed requirements

2

3

6

Mechanical

Weight exceeds requirement

3

1

3

Table 4: The list of risks after you’ve rated the Severity and Probability of each one. The RPN is a measure of how important each risk is.

How and when should we respond to these risks?

After a few more days of letting things settle, bring the group together again. Your rules should state a threshold and all risks with an RPN above that number must have a mitigation that should move the RPN below the threshold. Looking at our example we’ll create mitigations for risks with an RPN more than 5.

Temperature exceeds material limits

It’s hard to imagine a situation where the temperature of the device exceeding your material limit not being very bad, so we’re better off attacking probability than severity. A solution to this might be to select a material that can tolerate very high temperatures or add a design element that effectively limits the maximum temperature.

Pressure vessel fails

Like the temperature risk, we’re better off going for probability. One possible approach is to do a finite-element analysis (FAE), which is a computer simulation of the forces on the device. If the FEA says our design is safe with a margin of 100%, we can set the probability to 1.

Power demand exceed requirements

Our initial calculations suggest that the power demand is likely to exceed what our marketing team wants by 20%. The marketing team says that 97% of the market can provide 30% more power than the current requirement and they’re okay with changing the requirement. Often the mitigation is changing a requirement, not the design.

Weight exceeds requirement

The RPN here is below our threshold, so there’s no need to create a mitigation plan.

When you’re done, you should have something like this:

Area

Risk/Opportunity

Sev

Prob

RPN

Mitigation

Thermal

Temperature exceeds material limits

5

2

10

Explore material choice and mechanism to limit maximum temperature

Mechanical

Pressure vessel fails

5

2

10

FEA

Electrical

Power demand exceed requirements

2

3

6

Increase power requirement

Mechanical

Weight exceeds requirement

3

1

3

Table 5: It’s common to include the Sev and Prob numbers you expect after mitigation in this chart.

Mitigate and monitor

It’s now time for the team to implement the mitigations. After an agreed amount of time the same team should meet and review the situation.

  • Have we selected a material or a control mechanism to lower the maximum temperature?

  • What did the FAE show about the forces on the pressure vessel?

  • Have we updated the requirements document with the new power requirements?

  • Have we learned of any new risks that we neglected previously?

In my example, I’ve focused on how things can unexpectedly go wrong, but the same process can be used on how sometimes things go better than expected. Capturing opportunities is almost as important as resolving risks.

The intention is to reduce risks and uncertainty early, because some of the mitigations might force a significant redesign, which is a lot easier early in the project. The FMEA is just the starting point. Go forth and reduce uncertainty and successfully deliver to your stakeholders’ delight!

Related articles

Learn how and when to create a risk register so you can take control of potential threats to your project through analysis and mitigation planning.

Explore More Content

Modern modular PPM solutions that scale with your business. Align your teams with the integrated platform that bridges the gap between strategy and execution.

Tempo Loop is the next evolution of PPM software. It continuously tracks work tied to the strategy it funded, so you don’t wait to find out about strategic drift in your next review. Know what every person and agent is working on and what it costs in real time.

Seamlessly connect ServiceNow with Power BI, transforming complex enterprise data into actionable insights and driving smarter, data-informed decisions across the organization

#1 Jira Time Tracking & AI Apps: Log Tempo Timesheets for Planning, Project Management & Billing. Plugin Office365, Google & Slack

Jira Project Portfolio Management (PPM): Visualize data and manage projects within spreadsheet-like tables — in less than a minute

Combining Tempo Timesheets and Structure PPM provides a unified view of time tracking and project progress, enabling more accurate reporting and effective portfolio management. Simplify workflows, enhance collaboration, and ensure projects stay on time and within budget.

Colleagues interacting around a desk

Effortlessly bridge Jira with your preferred BI tool, unlocking unparalleled insights and enhancing decision-making

Build and scale a custom ITSM solution at your own pace with Tempo's modular suite of integrated tools. Enhance Jira's capabilities and take control of your entire IT portfolio.

Adapt to changing business needs, rapidly adjust plans, and reallocate investment.

Gain a more complete project management solution, simplifying project reporting, improving collaboration, and ensuring projects stay on time and within budget.

Tempo’s intuitive automation and Jira-native design make it the most trusted time tracking tool for enterprise organization.

A powerful team resource management tool designed to optimize capacity planning and project management in Jira

Portfolio Manager integrates seamlessly with Jira to give you predictive scheduling, real-time scenario modeling, and advanced resource management – ensuring you stay on track, no matter what challenges arise.

Project financial management for Jira & Timesheets. Monitor project costs, expenses, revenue, billing & budgets. Track Capex/Opex

Connect AI spend to the work it delivers. Attribute AI coding-tool costs to Jira epics and prove AI ROI, inside Jira with Tempo Workforce Intelligence.

Extend your Jira with prebuilt and highly configurable reports for straightforward time tracking.

#1 Jira Resource Management App: Optimize team allocation, skillset utilization, capacity planning & project management

For planning leaders looking to add a big-picture roadmap view to their structured Jira data, this integration is essential. Improve visibility to leadership, reduce reporting admin, and keep your team aligned.

Integrate Jira with Google BigQuery to seamlessly export and sync data for advanced analytics and customized reporting

Capture human time and AI activity together in Jira so you can measure what your AI tools are truly contributing and costing.

Seamlessly manage project timelines and resources while accurately tracking time spent on tasks. This integration enhances visibility, improves planning accuracy, and supports data-driven decision-making for better overall project outcomes.

Visualize all your Jira data & manage portfolios of projects in real-time.

Monitor projects and portfolios to get simple, clear, and real-time views of your costs, budgets, and profits that can be shared throughout your entire organization.

Powered by Structure’s custom hierarchies, visualize your roadmap, project plans, timeline & dependencies within Jira Gantt charts

See how work is progressing and where blockers are with the most flexible reporting app in Jira.